NERC PRC-029-1: A Practical Guide to IBR Ride-Through Testing
NERC Compliance
IBR Modeling & Compliance
TECHNICAL INSIGHTS

NERC PRC-029-1: A Practical Guide to IBR Ride-Through Testing

Grid Interconnection
NERC Compliance
By
GridTech Solutions
·
September 17, 2026
NERC PRC-029-1 ride-through testing for solar, wind, and battery energy storage resources

What Solar, Wind, BESS, and Hybrid Resource Owners Need to Know About PRC-029-1 Compliance, PSS®E Modeling, PSCAD Studies, and Ride-Through Evaluation

As inverter-based resources (IBRs) continue to expand across the North American power system, ensuring that these facilities remain connected and support the grid during disturbances has become increasingly important.

NERC Reliability Standard PRC-029-1 — Frequency and Voltage Ride-through Requirements for Inverter-based Resources establishes ride-through and performance requirements for applicable solar photovoltaic (PV), battery energy storage systems (BESS), wind, and hybrid IBR facilities.

The purpose of PRC-029-1 is to ensure that IBRs ride through defined voltage and frequency excursions and support the Bulk Power System (BPS) during and after those events.

For Generator Owners, PRC-029-1 readiness involves much more than comparing inverter protection settings against voltage and frequency curves.

A comprehensive engineering evaluation may require review of:

  • inverter protection and control settings;
  • power plant controller (PPC) settings;
  • balance-of-plant protection;
  • OEM ride-through capability;
  • PSS®E or PSLF dynamic models;
  • PSCAD/EMT models;
  • voltage and frequency ride-through simulations;
  • active and reactive power response;
  • phase-angle-jump and RoCoF behavior; and
  • post-disturbance recovery.

This article provides a practical engineering framework for evaluating an IBR facility against PRC-029-1.

What Is NERC PRC-029-1?

PRC-029-1 establishes frequency and voltage ride-through requirements specifically for inverter-based resources.

The standard applies to Generator Owners and covers:

  • Bulk Electric System (BES) IBRs, and
  • certain non-BES IBRs that have or contribute to an aggregate nameplate capacity of at least 20 MVA and are connected through a system designed primarily to deliver that capacity to a common point of connection at 60 kV or higher.  

PRC-029-1 is organized around four principal requirements.

R1 — Voltage Ride-Through

The Generator Owner must ensure that each applicable IBR is designed and operated to meet or exceed the voltage ride-through requirements within the applicable must Ride-through zone, subject to the exceptions specified in the standard.

R2 — Voltage Disturbance Performance

R2 goes beyond simply remaining connected.

During voltage excursions, the IBR must provide the required real-power, reactive-power and current response and meet specified post-disturbance recovery performance.

R3 — Frequency Ride-Through

The IBR must meet the applicable frequency ride-through requirements when system frequency remains within the Attachment 2 must-ride-through zone and the absolute rate of change of frequency (RoCoF) is less than or equal to 5 Hz/second, unless an applicable documented hardware limitation exists.

R4 — Existing Hardware Limitations

R4 establishes a documentation process for applicable existing IBRs with known physical hardware limitations that prevent compliance with portions of R1 through R3.

PRC-029-1 Compliance Is More Than a Protection Curve Review

A common first step in evaluating ride-through capability is to compare inverter undervoltage, overvoltage, underfrequency, and overfrequency protection settings against the PRC-029-1 ride-through envelopes.

That comparison is important—but it may not be sufficient for a plant-level evaluation.

Voltage can vary considerably throughout an IBR facility.

For example:

Transmission System → Main Power Transformer → Collector System → GSU Transformer → Inverter

A disturbance measured at the high side of the main power transformer may therefore result in a different voltage at the inverter terminals because of transformer impedance, collector-system impedance, reactive-current injection, inverter controls, and other electrical characteristics.

PRC-029-1 itself recognizes dynamic simulations, studies, plant protection settings, and control-setting design evaluations as examples of evidence that may demonstrate design capability.

For that reason, an effective PRC-029-1 assessment should consider the entire facility, not simply the inverter trip settings.

A Practical PRC-029-1 Engineering Evaluation Process

The proposed PRC-029-1 IBR Ride-Through Design Evaluation Implementation Guidance provides a useful engineering framework for evaluating facility capability.

The overall process can be organized into six major steps:

1. Collect and verify as-left facility data
2. Coordinate with inverter and PPC OEMs
3. Review protection and control settings
4. Verify PSS®E/PSLF and PSCAD models
5. Perform ride-through simulations
6. Implement corrective actions and document final results

It is important to distinguish the two source documents: PRC-029-1 is the Reliability Standard, while the April 27, 2026 implementation guidance reviewed for this article is identified as proposed and not ERO Enterprise endorsed. Its example study methodology should therefore not be interpreted as a prescriptive NERC test procedure.

Step 1 — Collect and Verify As-Left Facility Data

A PRC-029-1 evaluation should begin with the facility's actual as-left configuration.

The engineering team should collect and review available information such as:

  • latest single-line diagrams;
  • main power transformer data;
  • collector-system configuration;
  • inverter make, model, and firmware;
  • inverter protection settings;
  • inverter control settings;
  • PPC settings;
  • balance-of-plant relay settings;
  • reactive compensation equipment;
  • existing PSS®E/PSLF models;
  • available PSCAD/EMT models; and
  • previous model-validation or commissioning reports.

The objective is to make sure the facility being simulated corresponds to the facility actually operating in the field.

Step 2 — Coordinate With the Inverter and PPC OEM

Some PRC-029-1 evaluations require information that may not be available in the standard interconnection model package.

Generator Owners may need to obtain additional information from the inverter and PPC OEM, including:

  • maximum voltage ride-through capability;
  • maximum frequency ride-through capability;
  • actual LVRT/HVRT settings;
  • LFRT/HFRT settings;
  • RoCoF protection;
  • phase-jump protection;
  • anti-islanding logic;
  • consecutive-disturbance capability;
  • voltage and frequency measurement filtering;
  • active/reactive current-priority logic; and
  • validated or verified dynamic models.

OEM coordination becomes particularly important if the initial engineering assessment identifies protection or control settings that may need modification.

Step 3 — Review Inverter, PPC, and Balance-of-Plant Protection

An inverter may be capable of riding through a disturbance while another protection system disconnects the facility.

The evaluation should therefore consider protection throughout the plant.

Inverter Protection

Review should include:

  • undervoltage protection;
  • overvoltage protection;
  • underfrequency protection;
  • overfrequency protection;
  • RoCoF protection;
  • phase-jump protection;
  • anti-islanding protection; and
  • voltage/frequency measurement filtering.

PRC-029-1 also specifies that instantaneous trip settings based on instantaneously calculated voltage measurements using filtering shorter than one cycle (16.6 milliseconds) are not permissible.

Balance-of-Plant Protection

The assessment may also need to consider:

  • collector feeder relays;
  • MV bus protection;
  • HV bus protection;
  • transformer protection;
  • capacitor/reactor protection;
  • tie-line protection; and
  • V/Hz protection.

The objective is to identify any protection function capable of disconnecting all or part of the IBR during a required ride-through event.

Step 4 — Verify the PSS®E/PSLF and PSCAD Models

Before performing PRC-029-1 simulations, the engineering models should be checked against the facility's actual configuration.

Steady-State Network Verification

Verify parameters such as:

  • main power transformer impedance and ratings;
  • transformer taps;
  • GSU transformer data;
  • collector-system equivalent;
  • shunts and reactive compensation;
  • facility topology; and
  • active/reactive power capability.

Dynamic Model Verification

For the inverter and PPC models, review parameters such as:

  • active and reactive power limits;
  • current limits;
  • active/reactive current priority;
  • reactive-current injection;
  • K-factor or equivalent voltage-support parameters;
  • LVRT/HVRT thresholds;
  • LFRT/HFRT thresholds;
  • voltage/frequency protection;
  • active-power recovery; and
  • ramp-rate limits.

The model used for PRC-029-1 evaluation should represent the as-left plant behavior as accurately as practical.

PSS®E vs. PSCAD for PRC-029-1

Both phasor-domain transient simulation and electromagnetic transient simulation can have roles in a PRC-029-1 evaluation.

PSS®E/PSLF can be used for many plant-level voltage, frequency and recovery studies where an appropriately verified positive-sequence model captures the relevant behavior.

PSCAD/EMT analysis becomes particularly valuable when the evaluation depends on fast inverter controls, PLL behavior, phase-angle jumps, sequence behavior, unbalanced faults, or detailed protection logic.

The appropriate study platform should therefore be selected based on the phenomenon being evaluated and the availability and quality of the applicable models.

Step 5 — PRC-029-1 Ride-Through Simulation Test Matrix

Based on PRC-029-1 and the example engineering approach presented in the proposed implementation guidance, GridTech recommends organizing the facility-level evaluation around the following test categories.

PRC-029-1 Ride-Through Evaluation Matrix

\"NERC

PRC-029-1 LVRT and HVRT Requirements

Voltage ride-through should be evaluated against the applicable Attachment 1 criteria.

For PV, BESS, and other IBRs covered by Table 2, the standard specifies the following voltage regions and minimum ride-through times:

\"PRC-029-1

These values apply to the \"all other IBR\" category in Table 2; AC-connected Type 3 and Type 4 wind IBRs covered by Table 1 have different low-voltage durations.

The applicable voltage is evaluated using the voltage at the high side of the main power transformer, with additional measurement details established in Attachment 1.

PRC-029-1 LFRT and HFRT Requirements

Frequency ride-through should be evaluated separately from voltage ride-through.

Attachment 2 establishes the following frequency-versus-time requirements:

\"PRC-029-1

Frequency is measured at the high side of the main power transformer. The standard states that frequency is measured over a period of time, typically 3–6 cycles, and instantaneous or single-point measurements may not be used in determining control settings.

These tests allow engineers to evaluate LFRT and HFRT separately from RoCoF behavior.

LFRT/HFRT and RoCoF Are Not the Same Test

This distinction is important.

LFRT/HFRT

These tests evaluate whether the IBR remains connected for the required frequency magnitude and duration.

For example:

60 Hz → 58.8 Hz → lower-frequency region → recovery

or

60 Hz → 61.2 Hz → higher-frequency region → recovery

The response is compared against Attachment 2.

RoCoF

The RoCoF evaluation addresses how quickly frequency changes.

R3 applies when the absolute RoCoF magnitude is less than or equal to 5 Hz/second, with RoCoF calculated as an average over multiple calculated system frequencies for a period of at least 0.1 second; the standard specifies that RoCoF is not calculated during fault occurrence and clearance.

A facility can therefore have acceptable LFRT/HFRT protection thresholds while still requiring evaluation of its response to a rapid frequency ramp.

Active Power Recovery and Reactive Current Response

One of the most significant changes for engineering evaluation is that remaining connected does not by itself demonstrate the required performance.

During a voltage disturbance, R2 requires the IBR to exchange current, up to its maximum capability to provide voltage support, on affected phases during symmetrical and asymmetrical disturbances. Reactive-power priority is the default unless real-power priority is required through other applicable mechanisms.

Following the disturbance, R2.5 establishes another important performance requirement.

The IBR must restore real-power output to the pre-disturbance or available level, whichever is less, within 1.0 second after voltage returns from the mandatory or permissive operation region to the continuous operation region, unless an applicable entity requires a different post-disturbance level or recovery time.

A PRC-029-1 simulation should therefore evaluate more than a simple PASS = no trip criterion.

Engineers should review:

Voltage → Current → Reactive Power → Active Power → Protection → Recovery

Consecutive Fault Ride-Through

PRC-029-1 also requires attention to repeated disturbances.

Attachment 1 specifies that the durations of mandatory and permissive operating regions are cumulative over one or more disturbances within any 10-second period. It also addresses repeated deviations outside the continuous operating region.

Consequently, a comprehensive evaluation should consider whether:

  • inverter protection resets correctly;
  • temporary current blocking recovers correctly;
  • DC-link and inverter controls remain stable;
  • thermal/protection logic permits subsequent ride-through; and
  • the facility remains connected through the applicable consecutive disturbances.

OEM confirmation can be particularly important because not every internal hardware or protection limitation is represented in a standard positive-sequence model.

Phase-Angle Jump Evaluation

PRC-029-1 contains a specific R1 exception associated with an instantaneous positive-sequence voltage phase-angle change of more than 25 electrical degrees at the high side of the main power transformer when initiated by a non-fault transmission-system switching event.

An EMT-based phase-angle-jump evaluation can examine:

  • PLL response;
  • inverter synchronization;
  • phase-jump protection;
  • anti-islanding logic;
  • current blocking;
  • control stability; and
  • unintended inverter tripping.

This is an area where PSCAD or another appropriate EMT platform can provide information not represented in a conventional positive-sequence simulation.

Asymmetrical Fault Testing

PRC-029-1 R2.2 specifically addresses current exchange during both symmetrical and asymmetrical voltage disturbances.

An EMT evaluation of asymmetrical faults can be used to examine:

  • phase-specific current response;
  • positive- and negative-sequence behavior;
  • current limiting;
  • voltage support;
  • PLL stability;
  • protection response; and
  • post-fault recovery.

For modern inverter-based plants, this can be an important component of demonstrating the facility's response beyond balanced three-phase disturbances.

Step 6 — Correct Deficiencies and Repeat the Evaluation

An initial failed simulation does not necessarily mean that major equipment replacement is required.

Potential corrective actions may include:

  • modifying inverter LVRT/HVRT settings;
  • modifying LFRT/HFRT settings;
  • adjusting RoCoF protection;
  • adjusting phase-jump protection;
  • reviewing anti-islanding logic;
  • changing voltage/frequency filtering;
  • adjusting PPC protection;
  • changing active/reactive current priority;
  • adjusting reactive-current injection;
  • modifying active-power recovery parameters;
  • changing BOP relay settings; or
  • implementing OEM-approved firmware/control updates.

Following corrective actions, the applicable dynamic models should be updated and the affected tests repeated.

The final engineering package should clearly document the difference between the original as-left configuration, the identified deficiency, the corrective action, and the final compliant configuration.

What if the IBR Has a Hardware Limitation?

For an applicable IBR already in service by the effective date, R4 establishes a process for qualifying known hardware limitations that prevent the facility from meeting portions of R1 through R3.

The required documentation includes:

  • IBR identification;
  • the specific ride-through requirements that cannot be met;
  • actual hardware capability;
  • identification of the hardware causing the limitation;
  • technical documentation showing that physical hardware replacement is required and that the limitation cannot be remedied through software or setting changes; and
  • information concerning plans to remedy the limitation, if applicable.  

This makes the distinction between a setting limitation and a true hardware limitation particularly important.

Build the PRC-029-1 Compliance Evidence Package

PRC-029-1 explicitly recognizes evidence such as:

  • dynamic simulations;
  • engineering studies;
  • plant protection settings; and
  • control-setting design evaluations.

The standard also requires applicable disturbance-monitoring evidence to demonstrate actual operational performance.

For R1, R2, and R3, evidence must be retained for 36 calendar months or the date of the last audit, whichever is greater. R4 evidence must be retained for five calendar years or the date of the last audit, whichever is greater.

A strong PRC-029-1 engineering package should therefore establish traceability between:

\"NERC

How GridTech Solutions Can Support PRC-029-1 Compliance

GridTech Solutions provides power-system modeling, dynamic simulation, model validation, and grid-compliance engineering services for inverter-based resources across North America.

Our PRC-029-1 engineering support can include:

  • PRC-029-1 applicability and gap assessment;
  • inverter and PPC protection/control review;
  • OEM technical coordination;
  • balance-of-plant protection review;
  • PSS®E and PSLF model review and verification;
  • PSCAD/EMT model review and simulation;
  • LVRT and HVRT studies;
  • LFRT and HFRT studies;
  • active and reactive power response studies;
  • post-fault active-power recovery analysis;
  • consecutive-fault ride-through studies;
  • RoCoF studies;
  • phase-angle-jump analysis;
  • symmetrical and asymmetrical fault analysis;
  • remediation and sensitivity studies; and
  • technical documentation supporting the Generator Owner's compliance evidence.

Our approach integrates protection settings, OEM capabilities, plant controls, dynamic models, and simulation results to evaluate the behavior of the complete IBR facility rather than relying solely on individual inverter protection curves.

Preparing Your Solar, Wind, or BESS Facility for PRC-029-1

PRC-029-1 represents an important evolution in North American IBR performance requirements.

For Generator Owners, the central question is no longer simply:

\"Are our inverter protection settings outside the no-trip zone?\"

A more complete engineering question is:

\"Will the entire facility remain connected, provide the required grid support, and recover appropriately when the power system experiences the voltage and frequency disturbances defined by PRC-029-1?\"

Answering that question requires coordination among facility data, OEM capability, protection settings, plant controls, PSS®E/PSLF and PSCAD models, and engineering simulations.

Starting the evaluation early provides time to identify model discrepancies, obtain missing OEM information, adjust protection and control settings where appropriate, perform remediation studies, and develop a defensible compliance evidence package.

Need Help With a PRC-029-1 Ride-Through Evaluation?

GridTech Solutions can support Generator Owners, developers, and asset managers with PRC-029-1 gap assessments, PSS®E and PSCAD modeling, LVRT/HVRT and LFRT/HFRT studies, RoCoF and phase-angle-jump evaluations, protection reviews, remediation studies, and engineering documentation.

Contact GridTech Solutions to discuss your IBR facility's PRC-029-1 readiness and ride-through study requirements.

Contact GridTech Solutions to discuss your project and reduce interconnection risk.

📞 Contact us: 501-298-4400
✉️ Email: info@gridtechsolution.com

Technical Disclaimer: This article is provided for general engineering information and does not constitute legal, regulatory, or compliance advice. PRC-029-1 itself should be used as the governing source for applicable requirements. References to the April 27, 2026 PRC-029-1 IBR Ride-Through Design Evaluation Implementation Guidance are based on a proposed document identified as not ERO Enterprise endorsed. The specific engineering evaluation required for a facility depends on its configuration, equipment capabilities, applicable requirements, and engineering judgment.

‍